The system of normal operation of the turbine section is being modernized at power unit No. 1 of the RNPP
24.05.2024
Until June 28 of this year, LLC Kuznetsov commissioning and installation enterprise "Elektropivdenmontazh" will carry out additional construction and installation work as part of the implementation of the safety improvement program "Modernization of the system of normal operation important for the safety of the turbine compartment" at power unit No. 1. This is reported on the Prozorro site.
This measure was previously implemented by the Varas enterprise at the power units of other Ukrainian nuclear power plants.
As part of the additional works, morally and physically outdated equipment of technological protection, blocking and signaling, control and measuring devices, cable connections, etc. will be replaced.
Project and estimate documentation was developed by Kharkiv "Energoproject".
The modernization carried out in its entirety aims to increase the indicators of reliability, operability and reliability, as well as to create conditions that will prevent violations of the normal operation of the power unit. In particular, to reduce the probability of erroneous operation of equipment due to erroneous (unauthorized) actions of personnel.